Engineering, Procurement and Construction (EPC) of a new engineered sanitary landfill facility and its infrastructure according to USEPA standards, to serve for proper disposal over 20 years of 125 T/day of commercial and household waste, to accommodate 500,000 m3 of waste.
Description of Work:
01/Earth moving works
02/ Construction of 60,000 m2 engineered sanitary landfill and leachate ponds (HDPE liner- smooth & textures; Geotextile; Geocomposite; clay liner, Geonet; Geogrid)
03/ Composting of a guard house; administrative building; steel structures; repair shop; access roads, parking area; landscaping; peripheral fence, …
04/ Installation of two (2) weighbridges and a tyre wash facility
05/ Construction of mineral base liner (sealing) and/or artificial geological barrier according to the EU landfill directive or equivalent mineral sealing with a size of (50,000) m2, including completion of a landfill basic liner or equivalent constructions at a rate of (25,000) m2 per month.
06/ Construction of HDPE-Liner including welding of joints of (50,000) m2, including completion of a landfill basic liner or equivalent constructions at a rate of (25,000) m2 per month.
07/ Construction of (11,800) m2 asphalt roads.
08/ Construction of (7) buildings with (7,400) m3 building volume.